Useful Links

Useful Links

Parliament Hill School

High achieving and happy

New Build

Show list Show Grid

 17 July 2017

Following last week’s public consultation event, the presentation boards from Farrans and GSS are live on the Camden project webpage:
www.camden.gov.uk/phillwellis
September 2017

October 2017

A new planning application was submitted to Camden in October. The design has been revisited to ensure that the school buildings will enable Parliament Hill and William Ellis to deliver their curriculum and education vision, and at the same time provide the best value.

View the application by visiting www.camden.gov.uk/planning and enter the planning reference number 2017/5395/P in the New Planning search tool box.

 

 

New Building Development Timeline - Amended October 2017

Task

Estimated start

Estimated completion

Getting ready and setting up works

January 2018

February 2018

Construction of LaSWAP building

January 2018

August 2018

Construction of the new PHS teaching block and sports hall

February 2018

August 2019

WES new building

February 2018

October 2018

Refurbish PHS dining hall

July 2018

February 2019

Relocate PHS server to dining hall

July 2018

August 2018

Demolish Heath building

External landscaping works

August 2019

March 2020

 January 2018

January 2018- Newsletter | PDF

For enquiries or questions regarding our building works, please email us on PHSbuildingproject@parliamenthill.camden.sch.uk

June 2018

School Building Project Risk Register | PDF